Crews are moving right along in Phase 2 and mainline construction in Zone 1 is expected to be finished by the end of July. Due to a shipping delay on equipment, the first customers are anticipated to have service in late August.
Between 3rd Street and East Walnut, in Zone 2, our construction partners have placed all the duct work and will bring in an additional crew next week to complete their portion of the work and cleanup in the area. Residents and businesses can anticipate seeing crews south of East Walnut Street, in Zone 3, next week.
Anyone considering service is encouraged to act now to get on our priority service list and reduce the disruption to the neighborhood. Residents interested in service should enter their address and submit the form or call 888.961.6144. Registrants in Zone 1 will get their first month free*. There’s still time to register for two months free in Zones 2-4. The Zone 2 priority deadline is fast approaching on July 29!
* Promo applies to 1 Gbps or 2 Gbps service and Managed WiFi.
Related Articles

- News & Events
Junction City Among First Markets of Its Size to Gain Access to 2 GBPS Fiber Internet
Read Article
- News & Events
Renee Salzman Named 2023 Twin Valley Photo Contest Winner
Read Article
- News & Events